Project Summary

The Diamond Street Slope Stabilization project was designed to repair a surficial failure located on three parcels in the Lower Diamond Crestview area of Laguna Beach. Project included: removal of the failure in accordance with Geo Firm Report, the installation of all improvements including the caisson supported retaining wall and the retaining wall along Diamond Street; installation of all drains and utilities, and replacement of compaction fill; Installation of a natural rock veneer on the retaining walls and landscaping.

Services Involved:

  • Construction Management
  • Construction Inspection

Project Start
September 2014

Project End
November 2014

Project Value
$500,000
*Rendered within schedule & budget

Team
Project Manager: Scott Porterfield
Construction Manager: Syl Egan

Agency
City of Laguna Beach